Thursday, August 21, 2008

Quarter Sawn Oak Trim

The interior of our large addition to our house is going to be a little different than the "forest" look that we have in the timber frame current portion of the house. What I mean is that there will be less wood and less Southern Yellow Pine. I said the "forest look" because Stephanie sometimes comments on the over abundance of wood with all the rough cut timbers, pine flooring, trim, pine ceiling etc. It could all be complete if we installed a wood toilet seat and one of those high end wood bath tubs ;)

So we are going for a 1910 Craftsman large bungalow interior look on the addition with more drywall but plenty of trim. If one is to execute this properly you need a lot of Quarter Sawn Oak. We are doing this the traditional way and using oak in the formal or public rooms (entry, living room and family room) and then clear pine in the bedrooms etc. It is all coming from trees milled on site. The pine is from the property and the oak is a mix of trees I cut and some that Mr. M our excavator dropped off for us a while back.


The oak is mainly Red Oak and diameters randing from 24 to 48 inch. As you can imagine this can pose a problem trying to saw up a 48 inch diameter log. This is where the quarter sawing process comes into play. First I need to quarter the log into 4 equal sections and this is done using a chain saw on the large logs. This itself can take and hour or more to rip a large logs lengthwise. Once a section is on the mill there are various ways to skin a cat or cut the quarter section. The basic idea is to have the saw blade perpendicular to the rings in the section of log, giving vertical straight grain boards. I found this great example of quarter sawn oak (to the right) at the Tree Frog Furniture blog. The ultimate goal is to end up with a bunch of boards that have been cut with the grain straight and medullary rays exposed (see the example below). These are basically the tubes that go from ring to ring in the tree. It is one of those things that when you see it you know what I am talking about. I was afflicted with an obsession about quarter sawn oak about 12 -15 years ago when I first started making Mission furniture during graduate school. It has progressed to the point where whenever Stephanie and I would move to a new town I would seek out the local small town sawyer and try and get all the quarter sawn material they had. Id even pay for the material in advance. Then it progressed to looking for the random quarter sawn oak boards in strip flooring when walking through a room or the trim in all the auditoriums that I sit in listening to endless talks.
The sawing is all done on our Lumbermate 2000 sawmill, which has paid for itself many times over. This is a completely manual mill so it requires a little work to move the logs around but for the amount I use it, it gets the job done. Instead of considering it a stand alone saw mill I see it as part of my wood shop, especially since it is permanently located at the back end of the shop. Soon it will even get some work as I cut some veneer for the interior and exterior doors I am working on for the house.The oak is stacked and stickered right off the mill and once there is a pile that is 1000 to 1200 board feet (12"X12"X1") it is placed in the solar kiln for 5-6 weeks of drying. This brings the moisture level of the wood down to 6-8% and it is ready for use.
Finally, I have the finished product which is a whack (a technical term for a lot) of quarter sawn dry boards that I can plane, edge, stain, seal and use to finish all the trim work and other furniture projects that have been started but not completed.



Labels: , , ,

Friday, November 23, 2007

Completing the barn (Part 1)

With the long holiday weekend we wanted to try and finish up the last items on the barn punch list so we can get the building inspector out of here. The board and batten siding needs to go up, a few more 2x4 braces between the trusses and a a few more screws in the tin roof. I can only imagine what the building department thought when I pulled a permit for the barn. This is probably the only pole barn ever in Chatham County that a building permit has been pulled for. It was not a big deal since there are only 2 inspections.


To recap it is a 36x46 ft pole barn with a 4/12 roof. We set it up with the last 10 feet of the barn as a covered sawmill site. This is where we are going to keep our Norwood Lumbermate 2000 which has provided much of the timber and lumber, including trim and floors, for our timber frame house. It seems luxurious to be sawing under roof with all my tools at hand. We have about 100 southern yellow pine logs ready to cut on the mill. They came from the barn clearing. First at hand is the board and batten siding.


For the last few days I have been using the services of my two favorite helpers (Jacob,6 (L) and Joshua, 7 (R)). They do a great job emptying the saw dust bucket and tailing on the mill. They are liking the barn as much as me and have spent hours climbing ladders and swinging on the swing that we hung from the trusses.


The barn is going to be a work and staging area for our house addition which we hope to kick off in January. We enjoy our timber frame home but are starting to feel a bit cramped in 1100 sq ft of living space given we are a family of 4. If we only lived in the 1950's we would be set size wise.


Jeff and his son Christian was back on the job again. He has not been out here working since the middle of summer. Jeff is a skilled jack of all trades and he does all things construction from framing to granite counter tops. We got one of the 3 exterior walls done and have two more to do and plan on completing them tomorrow.


To be continued....


Labels: , ,

Tuesday, September 11, 2007

The Barn Project Continued

Last time on BMR we were placing the roof trusses. With that complete we were able to tie everything together with the hurricane straps, apply skip sheathing and place the tin roof.
The roof came from Construction Metal Products in Statesville, NC. It is the same place we got the roof for the house. It is of the galvalume type and unpainted. We suspect that it will also sound great in the rain but there has been none (or very little) for close to a month.


Ed M. came back with the mini excavator and we ran 180 ft of conduit (2" and 1") as well as water up to the barn for modern conveniences such as 100 AMP power, water, cable phone etc. It was a long weekend where we put about 20 hrs on the rented track hoe, but it was well worth it. We also moved tons of dirt to level the place out and create a better log lot (In the picture on the right you can see some of the logs from the clearing and the log lot area). The saw mill will be housed under this end of the mill with a 36 ft wide opening for bringing logs and cut wood in and out.



With the roof on, power connected and water running it was time for lights and outlets. We ran a few 20 AMP outlets and some overhead lighting, but left plenty of room for other circuits. As we work on placing the horizontal 2x4's for the siding it is nice to have plenty of power and electricity for a box fan.


Remaining items to complete before the final inspection on the barn are the following:

1. final row of screws on the roof

2. a few lag bolts on the posts

3. 27 sheets of sheathing to go up on the walls

4. general clean up


A piece of cake.....???






Labels: ,